Progress September 2006 - January 2007
Construction
began in February 2005. Earthwork, foundations, structural
steel, and floor decks were completed in 2005. Roofing,
exterior panels, glazing, and system rough-in were
complete by June 2006.
Interior framing and sheetrock were complete by September
2006. Interior framing, sheetrock and underground utility connections were completed in September 2006. Painting, ceilings, flooring, lighting, plumbing and laboratory casework and equipment should be completed by January 2007. Laboratory systems and building systems commissioning and final closeout will progress in February and March 2007.
|